The bridge is planned to be completed in 2016

Eight piles have been hammered down at a depth of 32 meters for the railway bridge which is being constructed across the Astara River, Nadir Azmammadov, spokesman for the Azerbaijan Railways CJSC.

Around 100 machineries are involved in the work on the territory, which has a rugged relief. It is necessary to construct 14 drainage systems for wastewaters here.

Additionally, work is underway to transfer power transmission lines and gas pipelines in the territory.

The transfer of the houses located in the construction territory will start soon.

Azmammadov added that the construction of the railway line and the bridge is planned to be completed before late 2016.

Date
2016.05.28 / 12:35
Author
Axar.az
See also

Armenia imports gasoline, diesel via Azerbaijan

Rainy weather is expected tomorrow

Azerbaijan sends another humanitarian aid to Iran - Photo

Ilham Aliyev responds to Pezeshkian’s message of thanks

Sheikh-ul-Islam meets Iran ambassador in Azerbaijan

Heavy rain and strong winds expected tomorrow

Azerbaijan and Turkiye to hold joint military training - Video

Aliyev: Zangezur corridor nearly complete

Mild winds with occasional fog expected tomorrow

Azerbaijan relocates 27 more families to Kalbajar city

Latest
Xocalı soyqırımı — 1992-ci il Bağla
Bize yazin Bağla
ArxivBağla