The bridge is planned to be completed in 2016

Eight piles have been hammered down at a depth of 32 meters for the railway bridge which is being constructed across the Astara River, Nadir Azmammadov, spokesman for the Azerbaijan Railways CJSC.

Around 100 machineries are involved in the work on the territory, which has a rugged relief. It is necessary to construct 14 drainage systems for wastewaters here.

Additionally, work is underway to transfer power transmission lines and gas pipelines in the territory.

The transfer of the houses located in the construction territory will start soon.

Azmammadov added that the construction of the railway line and the bridge is planned to be completed before late 2016.

Date
2016.05.28 / 12:35
Author
Axar.az
See also

Ilham Aliyev made Novruz holiday post

Mehriban Aliyeva shared Novruz holiday post

Allahshukur Pashazada to attend funeral of Georgia’s Catholicos

Weather forecast for March 21

Kazakhstan receives all expert reports for AZAL Aktau crash

Israeli embassy congratulates Azerbaijan on Ramadan Holiday

Ilham Aliyev shared Ramadan holiday post - Photo

Azerbaijan marks Ramadan Holiday

Weather forecast for the holidays

Azerbaijan sent 488 tons of grain to Armenia

Latest
Xocalı soyqırımı — 1992-ci il Bağla
Bize yazin Bağla
ArxivBağla