The bridge is planned to be completed in 2016

Eight piles have been hammered down at a depth of 32 meters for the railway bridge which is being constructed across the Astara River, Nadir Azmammadov, spokesman for the Azerbaijan Railways CJSC.

Around 100 machineries are involved in the work on the territory, which has a rugged relief. It is necessary to construct 14 drainage systems for wastewaters here.

Additionally, work is underway to transfer power transmission lines and gas pipelines in the territory.

The transfer of the houses located in the construction territory will start soon.

Azmammadov added that the construction of the railway line and the bridge is planned to be completed before late 2016.

Date
2016.05.28 / 12:35
Author
Axar.az
See also

3.3 magnitude earthquake hits Caspian Sea

Cloudy and dry weather expected tomorrow

Official luncheon hosted in honor of Latvian President

Mutual Azerbaijani-Armenian visits help normalize ties

Mother of school attacker arrested in Turkiye

Iran rejects claims of planned operations in Azerbaijan

Latvia’s president pays tribute to Heydar Aliyev

Israel hopes to further strengthen relations with Azerbaijan

Azerbaijani man killed in Russia-Ukraine war - Photo

New families arrive in Girmizi Bazar in Khojavend

Latest
Xocalı soyqırımı — 1992-ci il Bağla
Bize yazin Bağla
ArxivBağla