The bridge is planned to be completed in 2016

Eight piles have been hammered down at a depth of 32 meters for the railway bridge which is being constructed across the Astara River, Nadir Azmammadov, spokesman for the Azerbaijan Railways CJSC.

Around 100 machineries are involved in the work on the territory, which has a rugged relief. It is necessary to construct 14 drainage systems for wastewaters here.

Additionally, work is underway to transfer power transmission lines and gas pipelines in the territory.

The transfer of the houses located in the construction territory will start soon.

Azmammadov added that the construction of the railway line and the bridge is planned to be completed before late 2016.

Date
2016.05.28 / 12:35
Author
Axar.az
See also

ADEX 2026, Securex Caspian exhibitions conclude in Baku

Azerbaijan, Turkiye Defense Ministers attend ADEX 2026 - Photo

Armenia detains Azerbaijani citizen for two months

Azerbaijan, Turkiye, Georgia discuss regional security - Video

Azerbaijani citizen killed in Kyiv laid to rest in Kurdamir

Azerbaijan, Turkiye Defense Ministers met in Shusha - Photo

Azerbaijan to participate in Eurovision 2027

September temperatures exceed climate norm in Azerbaijan

AZAL receives second Airbus A321neo of 2026 - Photo

Rainy weather is expected tomorrow

Latest
Xocalı soyqırımı — 1992-ci il Bağla
Bize yazin Bağla
ArxivBağla