The bridge is planned to be completed in 2016

Eight piles have been hammered down at a depth of 32 meters for the railway bridge which is being constructed across the Astara River, Nadir Azmammadov, spokesman for the Azerbaijan Railways CJSC.

Around 100 machineries are involved in the work on the territory, which has a rugged relief. It is necessary to construct 14 drainage systems for wastewaters here.

Additionally, work is underway to transfer power transmission lines and gas pipelines in the territory.

The transfer of the houses located in the construction territory will start soon.

Azmammadov added that the construction of the railway line and the bridge is planned to be completed before late 2016.

Date
2016.05.28 / 12:35
Author
Axar.az
See also

Two Azerbaijanis killed in Iran Ian strike on Israel - Photo

Weather forecast for March 11

Baku ensures safe return of citizens amid regional conflict

No Azerbaijanis reported among victims of attacks in Iran

Around 200 Azerbaijani citizens to return from Middle East

Azerbaijan sends humanitarian aid to Iran - Video

Today Azerbaijan marks Wind Tuesday

Direct flights from Baku to Nakhchivan to resume March 9

Nakhchivan International Airport resumed operations - Photo

Cargo transport between Azerbaijan and Iran resumes

Latest
Xocalı soyqırımı — 1992-ci il Bağla
Bize yazin Bağla
ArxivBağla