The bridge is planned to be completed in 2016

Home page Society
12 Punto 14 Punto 16 Punto 18 Punto

Eight piles have been hammered down at a depth of 32 meters for the railway bridge which is being constructed across the Astara River, Nadir Azmammadov, spokesman for the Azerbaijan Railways CJSC.

Around 100 machineries are involved in the work on the territory, which has a rugged relief. It is necessary to construct 14 drainage systems for wastewaters here.

Additionally, work is underway to transfer power transmission lines and gas pipelines in the territory.

The transfer of the houses located in the construction territory will start soon.

Azmammadov added that the construction of the railway line and the bridge is planned to be completed before late 2016.

Date
2016.05.28 / 12:35
Author
Axar.az
See also

Chinese official visits Yerevan for talks

Azerbaijan to mark 150th anniversary of Fatali Khan Khoyski

Tokayev receives Sheikhulislam Allahshukur Pashazade

Weather forevast for September 18

U.S.: Do not travel to the border region with Azerbaijan

Georgia pays off 'historic debt' to Azerbaijan

Trump criticizes an Australian journalist

Unstable weather to continue in Azerbaijan

Trump: Zelensky will have to sign a ceasefire with Russia

Turkiye and Armenia to restore Arpachay bridge

Latest
Xocalı soyqırımı — 1992-ci il Bağla
Bize yazin Bağla
ArxivBağla