The bridge is planned to be completed in 2016

Home page Society
12 Punto 14 Punto 16 Punto 18 Punto
The bridge is planned to be completed in 2016

Eight piles have been hammered down at a depth of 32 meters for the railway bridge which is being constructed across the Astara River, Nadir Azmammadov, spokesman for the Azerbaijan Railways CJSC.

Around 100 machineries are involved in the work on the territory, which has a rugged relief. It is necessary to construct 14 drainage systems for wastewaters here.

Additionally, work is underway to transfer power transmission lines and gas pipelines in the territory.

The transfer of the houses located in the construction territory will start soon.

Azmammadov added that the construction of the railway line and the bridge is planned to be completed before late 2016.

Date
2016.05.28 / 12:35
Author
Axar.az
See also

Azerbaijan and Turkiye hold high-level military dialogue

Weather forecast for December 3

Azerbaijan prioritizes economy and regional projects

UAVs proved key in the 2020 Karabakh war - CNN

Baku opens outdoor ice rink for New Year - Video

Rain and fog reported across multiple regions

Russia announces updated Ukrainian losses

Restoration and reconstruction continue in Khankendi

Weather forecast for December 2

Aliyev shared post on anniversary of liberation of Lachin - Video

Latest
Xocalı soyqırımı — 1992-ci il Bağla
Bize yazin Bağla
ArxivBağla