Azerbaijan continuing power system rehabilitation program

Home page Society
12 Punto 14 Punto 16 Punto 18 Punto
Azerbaijan continuing power system rehabilitation program

Repairs and restoration are being carried out at the Mingachevir Hydro Power Plant as part of the power system rehabilitation program of Azerenergy OJSC.

Axar.az reports citing the company.

An autotransformer with a 220/110 kilovolt voltage and a force of 200 megavolts has been installed at the power plant.

Some 780 meters of 110-kilovolt power lines, stretching over the Kura River, have been laid. The lines have been connected to the new autotransformer.

The autotransformer is also equipped with a modern relay protection and automation.

Now, with the additional autotransformer it has become possible to carry out any repairs and ensure uninterrupted power supply.

Connecting the autotransformer has had a positive impact on the quality of the power supply to the city of Mingachevir and adjacent territories.

Date
2019.02.05 / 18:36
Author
Axar.az
See also

Pakistani diplomat evacuated from Iran via Azerbaijan - Photo

Weather forecast for March 15

First relocation convoy heads to Khanoba village

Baku hosts NATO course - Photo

MoD condemns missile launch against Turkiye

Weather forecast for March 14

Azerbaijani soldier killed in Russia-Ukraine war - Photo

Weather foresact for March 13

Swiss ambassador evacuated to Azerbaijan from Iran

Weather forecast for March 12

Latest
Xocalı soyqırımı — 1992-ci il Bağla
Bize yazin Bağla
ArxivBağla