Azerbaijan continuing power system rehabilitation program

Repairs and restoration are being carried out at the Mingachevir Hydro Power Plant as part of the power system rehabilitation program of Azerenergy OJSC.

Axar.az reports citing the company.

An autotransformer with a 220/110 kilovolt voltage and a force of 200 megavolts has been installed at the power plant.

Some 780 meters of 110-kilovolt power lines, stretching over the Kura River, have been laid. The lines have been connected to the new autotransformer.

The autotransformer is also equipped with a modern relay protection and automation.

Now, with the additional autotransformer it has become possible to carry out any repairs and ensure uninterrupted power supply.

Connecting the autotransformer has had a positive impact on the quality of the power supply to the city of Mingachevir and adjacent territories.

Date
2019.02.05 / 18:36
Author
Axar.az
See also

Azerbaijani President visits Devin Castle in Bratislava - Photo

Ilham Aliyev visits the Freedom Gate monument - Photo

Azerbaijan, Iran discuss deepening parliamentary relations

Ilham Aliyev holds expanded meeting with Slovak president

Bratislava–Baku direct flight may be launched

Rain expected tomorrow in Baku

Fog to limit visibility on highways on December 7

Heavy rain expected in Baku and regions

Ukraine updates Russian army losses

The weather forecast has been announced

Latest
Xocalı soyqırımı — 1992-ci il Bağla
Bize yazin Bağla
ArxivBağla